WE Report

Lessons Learned

Lesson Learned





By: Drilling Engineer

Report No.

4912

Discipline/Origin

Drilling
No origin

Well

Copernicus
6608/1-1 S

Date created

2022/09/20
1174 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Planning
Negative

Deepsea Yantai


What happened in Production section:
Time was spend circulating hole clean and even MW in/out.

What Was Planned

Circulate to get even MW in/out

What Was Learned

It is not needed to circulate, as long as there is clean mud in the pipe and the annulus is isolated by BOP failsafe valve during the test

What Actions Are Required

Use the established practice and line up previously applied on DSY to save time on FIT