Lesson Learned





No user selected

Report No.

184

Discipline/Origin

Drilling
No origin

Well

Serin
35/12-7

Date created

2019/02/05
2496 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Equipment
Negative

Transocean Arctic


What happened in Production section:
Had to lay out several joints due to missing threads on top of pin ends, (9 5/8″, #53.3, P-110, VAM21). On some sides on top of pin end, threads were totally missing. Ovality was also measured on some pin ends. Suspected manufacture fault. Pictures were taken and 4 joints were rejected from rig floor during MU, 21 joints were rejected on deck after inspection. (total of 16 jnts, 10% of casing sent out).