What happened in Surface section:
The centralizer placement on the 20” interfered with the rollers on the casing tong.

What Was Planned

M/U 20″ casing joints with tong.

What Was Learned

The centralizers were installed 1.35 m from PIN end for this job. The learning is that the centralizers should be installed at least 2 m further away from PIN end than what was done.

What Actions Are Required

Communicate learning to OCTG supplier early in planning phase.

This only applies to 20”.