Lesson Learned





No user selected

Report No.

375

Discipline/Origin

Drilling
No origin

Well

Shrek
6507/5-9 S, 6507/5-9 A

Date created

2019/10/22
2237 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Coring
Positive

Deepsea Nordkapp


What happened in Reservoir section:
Cores were retrieved successfully.

What Was Planned

FCS (full closure system) used for coring.

What Was Learned

System worked very well and high core % received at surface.
Works very well for very soft formation.

What Actions Are Required

Continue with this system in the future (if formation conditions permits).