WE Report

Lessons Learned

Lesson Learned





No user selected

Report No.

231

Discipline/Origin

Drilling
No origin

Well

Kallåsen
35/12-6 S

Date created

2019/02/07
2494 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Planning
Negative

Transocean Arctic


What happened in Rig move:
The rig move plan was written for using 4 AHVs. The actual rig move used 3 AHVs. Hence, the procedure was overall not applicable and plans had to be developed in real time on rig.

What Was Planned

Planned 4 AHVS

What Was Learned

The rig move plan should have been updated and re-written after it was known that only 3 AHVs were going to be used.

What Actions Are Required

In future, always make new rig move plan which takes into account the actual circumstances.

EDITOR


CLOSE LL (testing)





New Lesson Learned

You do not have permission to view this form.




\n\t\t

\n\t\t\t\n\t\t\t