WE Report

Lessons Learned

Lesson Learned



INTERNAL



By: Giacomo Bonomo

Report No.

1358

Discipline/Origin

Drilling
Own Experience

Well

Hemispheres
36/1-4

Date created

2021/03/04
1738 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Planning
N/A

Borgland Dolphin


What happened in Top hole:
Multiple requests for data raised during the creation of the model. The data requests were often received in an uncoordinated and fragmentary way. This lead to a shift in the dead line for the analysis.

What Was Planned

Conductor Analysis for Hemispheres well

What Was Learned

For the specific well, the issue did not led to major problems for the planning phase. Anyhow in case of operations with rigid time constraints , the delay in obtaining the study could lead to a delay in securing the LLI.
For the future it is recommended to agree prior the start of the analysis on the set of data required for the study, and start the modelization once all the data required are gathered.