By: Drilling Engineer

Report No.

5127

Discipline/Origin

Drilling
Own Experience

Well

Carmen
35/10-10S

Date created

2023/04/10
972 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Equipment
Negative

Deepsea Yantai


What happened in Surface section:
Not enough deckspace to place shoe and sting-in float. Had to be laid in riser bay.

What Was Planned

To measure the Shoe and Sting-in collar for 20″ Casing once onbaord the rig.

What Was Learned

Not enough deckspace to place shoe and sting-in float. Had to be laid in riser bay.

What Actions Are Required

Mitsui to provide measurements on tally list of sting-in float. Specify length of float and pups above/under.