Section N/A. What happened:
The BOP test tool was not ready to run. No DQ onboard and no status on the tool before they left the rig. The rig had a short 5 7/8″ LD to put on top of it

What Was Learned

That DQ should be instructed to make the tool ready to run if they are not going to be onboard for the BOP testing

What Actions Are Required

That DQ should be instructed to make the tool ready to run if they are not going to be onboard for the BOP testing