288

Discipline/Origin

Drilling
No origin

Well

Brasse
31/7-3 S

Date created

2019/10/02
2257 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Planning
Negative

Transocean Arctic


What happened in Top hole:
Had relatively short rig move where operations ended with OBM and next well started with WBM. Getting pits cleaned and bentonite spud mud mixed in time is a challenge.

What Was Planned

Mix spud mud on rig move.

What Was Learned

Should explore possibility of mixing some spud mud at the plant and shipping to the rig via PSV once on location. Common amongst other operators.

What Actions Are Required

If in same situation again, consider shipping spud mud on PSV.