WE Report

Lessons Learned

Lesson Learned





By: Drilling Engineer

Report No.

8285

Discipline/Origin

Drilling
No origin

Well

Tomcat
6501/10-1

Date created

2025/02/15
294 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Equipment
No classification

Deepsea Yantai


What happened in Surface section:
Set HAL suspension plug as pr HAL manual, plug depth +- 593 m. Pressure tested plug to 290 bar/10 min. Not able to disengage RT from plug. Called support and tried several times. Ended up releasing whole plug and POOH with same.

What Was Planned

Disconnect from intercept plug

What Was Learned

Low confidence in Interceptor plug. Poor quality on manual and instructions for running same. HAL rep (cementer) not trained in EQ. Documentation in Orlen/WE sharepoint poor.

What Actions Are Required

HAL to have better control of training of personnel for different EQ planned on well.
Supply documentation at an earlier stage and store at a suitable folder in Sharepoint in addition to HAL rep.
Prepare and update DOP.