Lesson Learned





By: Drilling Engineer

Report No.

5835

Discipline/Origin

Drilling
Own Experience

Well

Carmen
35/10-10S

Date created

2023/06/16
905 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Casing
Other

Deepsea Yantai


What happened in Surface section:
Crossovers supplied were of very different lengths: 4m, 6m and 12m.

What Was Planned

Mixed string of 9 7/8″ casing used for sidetrack utilising two threads VAM 21 and VAM TOP

What Was Learned

Different lengths mean that if for example a primary 4m crossover was damaged, requiring a 12m item to replace it as back-up, the whole casing tally could then be changed significantly, or pup joints required to make up the difference.

What Actions Are Required

Better to have the primary and back-ups of all crossovers roughly the same length.