WE Report

Lessons Learned

Lesson Learned





By: Drilling Engineer

Report No.

8207

Discipline/Origin

Marine
No origin

Well

Kjøttkake
35/10-13

Date created

2025/02/08
301 days ago

Project Phase

Project Phase

LL Type/Classification

No classification

Deepsea Yantai


What happened in :
Monkey fist not attached to wellhead running tool prior to rigging up. Had to wait for ROV to make and connect monkey fist to equipment online.

What Was Planned

ROV Monkey fist

What Was Learned

Should be done offline, when running tool still is on deck. Both Dril-Quip and Oceaneering have a bulletpoint in the preparation checklist to confirm monkey fist present. Also make sure the rope is long enough so that the ROV can access and grip it when the RT is landed, inside the SMO, with mud on top. If too short ROV is unable to find it if the current stirs up the mud inside the SMO

What Actions Are Required

Make sure every service company actually reads the dops and preparation checklist prior to operation.