WE Report

Lessons Learned

Lesson Learned





No user selected

Report No.

259

Discipline/Origin

Drilling
No origin

Well

Songesand
35/4-2

Date created

2020/06/16
1999 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Mud
Negative

Transocean Arctic


What happened in Reservoir section:
The cold temperature in the riser and 300 m below seabed made the WBM more viscous than under normal circumstances. This led to high ECD values when circulating: 1.36 sg EMW (FIT: 1.36 sg). The normal LWD had a lower flow range threshold of 1200 lpm. The tool could not be used and a low-flow LWD tool with flow range of 800 -1200 lpm was mobilized.

What Was Planned

Drill 8 1/2″ Section

What Was Learned

The lo-flow tool did not improve the situation. Turned out to be the mud which was causing the high ECD.

What Actions Are Required

In future, ensure proper simulations have been performed regarding the mud system to be used and the conditions it will be used in.