Lesson Learned





By: Lene Lomeland

Report No.

6765

Discipline/Origin

Drilling
No origin

Well

Falstaff
2/6-7 S

Date created

2024/09/23
439 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
No classification

What happened in Top hole:
After 2 ½ joints was driven in ground the rebound was observed to be very high, Blowcount was also rising.

What Was Planned

There was not planned for a cleanout, only as contingency if unable to get conductor to desired depth.

What Was Learned

Follow recommendation from crew. Following cleanout to 4 m less than planned depth allowed conductor to be driven to planned depth