WE Report

Lessons Learned

Lesson Learned





By: Drilling Engineer

Report No.

8206

Discipline/Origin

Drilling
No origin

Well

Tomcat
6501/10-1

Date created

2025/02/03
307 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Equipment
No classification

Deepsea Yantai


What happened in Top hole:
Fiberglass inner string broke off due to strong currents.

What Was Planned

POOH with WHRT and fiberglass cement stinger

What Was Learned

Evaluate to adjust rig position based on current prior to POOH or to do the cement job w/o inner string if strong current is expected in the area.

What Actions Are Required

Evaluate to do the cement job without inner string if strong currents are expected.