Section N/A. What happened:
QC time limit between receiving final cost estimates from vendors and submitting final AFE

What Was Learned

Include deadlines for final scope, to allow time to QC cost estimates against contract prior to submitting final AFE

What Actions Are Required

Include deadlines for final scope, to allow time to QC cost estimates against contract prior to submitting final AFE