What happened in Intermediate section:
Losses and pack off during the circulation. Total losses in the end with 100 lpm.

What Was Planned

Circulate prior to cement job.

What Was Learned

Went straight to cementing. Increased the flowrate prior to cement in annulus to ensure the cement was out of casing before setting up. Decreased the flow to minimum flow for good cement job displacement once spacer out of hole. Added LCM in spacer. Could see the pressure build up as spacer/cement in anulus. Due to wrong amount of cement additive in the cement slurry in the middle of job (extra retarder) it could not be deemed a barrier as the cement might not set up.

What Actions Are Required

Mix correct slurry.