WE Report

Lessons Learned

Lesson Learned





No user selected

Report No.

253

Discipline/Origin

Drilling
No origin

Well

Songesand
35/4-2

Date created

2020/06/16
1999 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Equipment
Negative

Transocean Arctic


What happened in Surface section:
The back-up 18 3/4″ wellhead assembly was sent out incomplete, without running tool, 9 m DP mandrel, equalizer sub and casing wiper plugs. The primary assembly, which was complete, measured 18 m.

What Was Planned

Back-up 18 3/4″ WH assy

What Was Learned

In order to use the back-up assembly, the mandrel with plugs (9 m) would have to pulled out of the primary assembly, making it 18 + 9 =27 m long. There is no deck space on the rig to accommodate this, virtually impossible to do offshore.

What Actions Are Required

Send out two complete wellhead assemblies in order to save rig time and have a realistic back-up if the primary is damaged.