WE Report

Lessons Learned

Lesson Learned





By: Drilling Engineer

Report No.

5141

Discipline/Origin

Drilling
Own Experience

Well

Carmen
35/10-10S

Date created

2023/04/13
969 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Equipment
Negative

Deepsea Yantai


What happened in Intermediate section:
Not approved pressure test. Downtime to drilling contractor.

What Was Planned

Pressure test TDS mud hose and boost line

What Was Learned

NPT on drilling contractor

What Actions Are Required

Approx. NPT cost = 520 833,- kr

EDITOR


CLOSE LL (testing)





New Lesson Learned

You do not have permission to view this form.