WE Report

Lessons Learned

Lesson Learned





By: Drilling Engineer

Report No.

5907

Discipline/Origin

Drilling
No origin

Well

Norma
25/7-11 S

Date created

2023/09/03
825 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Planning
N/A

Deepsea Yantai


What happened in P&A:
It was not clearly stated in the HLB cement program how the cement calculations should be carried out other than use of Enhanced method. After discussion with HLB onshore it was decided to calculate the cement/displacement with enhanced method placing the stinger above the cement+ excess cement. What previously done is to calculate the cement op with placing the stinger above the cement (not including the excess)

What Was Planned

The cement calculations to be done according to HLB cement Programme for the P&A and KO cement for mainbore.

What Was Learned

It should be clearly stated and agreed beforehand how to calculate the cement calculation to avid confusion.

What Actions Are Required

It should be clearly stated and agreed beforehand how to calculate the cement calculation to avid confusion.