WE Report

Lessons Learned

Lesson Learned





By: Drilling Engineer

Report No.

6456

Discipline/Origin

Drilling
Own Experience

Well

Gnomoria
35/10-12 S

Date created

2024/07/05
519 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
N/A

COSLPromoter

What happened in P&A:
Discussion about the risk of accidentally pulling the seal assembly free (no outer lock ring installed) with the wearbushing and even the casing as the casing weight was only 13 tons due to a shallow cut depth. Made decision to pull the wearbushing free with the annular BOP closed and check for pressure build up indicating potential for gas release from a pulled seal assembly.

What Was Planned

Pull the Dril-quip wearbushing

What Was Learned

Dril-quip state without the outer lock ring there is always a small risk that the wearbushing can pull the seal assembly free as the wearbushing is shear pinned to the seal assembly.

What Actions Are Required

Consider to close the annular BOP again under following circumstances 1) if outer lock ring is not installed, 2) suspected gas below the seal assembly.