WE Report

Lessons Learned

Lesson Learned





By: Karina Helle

Report No.

1223

Discipline/Origin

HSEQ
Experience Transfer Meeting

Well

Oselvar
A-1 H, A-2 H, A-3 HT2

Date created

2012/05/06
4962 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

QHSE
Positive

Borgland Dolphin


What happened in Production section:
DONG handover documentation: Due to LWD tool failures on previous reservoir sections it was decided to run a mud cooler. The mud cooler was circulating on sand trap 3. The reduced surface temperature (Mud out max 45 degr C / in 28 degr) resulted in much better work environment in the shakers, pit and pump rooms.

External Actions

Include mud cooler in future reservoir sections with high temperature.