Lesson Learned





No user selected

Report No.

377

Discipline/Origin

Drilling
No origin

Well

Shrek
6507/5-9 S, 6507/5-9 A

Date created

2019/10/22
2237 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

BOP
Negative

Deepsea Nordkapp


What happened in Reservoir section:
Waited for 30 minutes for annular relaxation after a P/T.

What Was Planned

Waiting for annular relaxation after a P/T.

What Was Learned

Possible to reduce this to 15mins. 30mins tends to come from the older 5k annulars with WBM/brine. Here we had a 10k and OBM.

What Actions Are Required

Evaluate if 15 minutes is worth the potential save compared to damaging rubber trying to RIH with tools/string.