WE Report

Lessons Learned

Lesson Learned





By: Lars Solvang

Report No.

2194

Discipline/Origin

Wireline / Slickline
Own Experience

Well

Oselvar
A-1 H, A-2 H, A-3 HT2

Date created

2021/10/04
1524 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Equipment
Negative

Borgland Dolphin


What happened in P&A:
Due to the missing clamps the control lines was coiled up around the tubing and made it impossible to pull the tubing. It was therefore necessarily to cut the tubing and pull it in section. It was therefore necessarily to cut the tubing shallow.

What Was Planned

The plan was to pull the completion (tubing) with control lines to surface.

What Was Learned

It was identified that cutting the tubing with explosive cutter near to surface could puncture the 9-5/8″ casing. It was possible that hydrocarbons under pressure was outside the casing. This would cause a well control incident.
It was also identified that using a explosive cutter would make shock waves up to the christmas tree that could damage it.

What Actions Are Required

It was decided to use a mechanical cutter.