Lesson Learned





By: Karina Helle

Report No.

1153

Discipline/Origin

Multidicipline
Experience Transfer Meeting

Well

Oselvar
A-1 H, A-2 H, A-3 HT2

Date created

2020/09/08
1915 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Experience Transfer Meeting
Negative

Borgland Dolphin


Section N/A. What happened:
Too little time for planning.
Not enough time for examination of the SSBoD.
Risks and mitigating actions not optimized.

What Was Planned

5 months planning time.

What Was Learned

Earlier engagement and handover.
More time needed for the SSBoD and risk mitigating actions.

What Was Done

Covered in Project risks (Risk ID 1)

External Actions

Actions Required for Oselvar: Secure enough time for planning and optimalization – > 6 months
Better review of risks and follow-up of mitigating actions.

What Was Done

Covered in Project risks (Risk ID 1)