Lesson Learned





By: Lene Lomeland

Report No.

6813

Discipline/Origin

Drilling
No origin

Well

Falstaff
2/6-7 S

Date created

2024/10/07
425 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Planning
Negative

What happened in Top hole:
Space out incorrect compared to Stack-up drawing from Well partner. The upper spool of the WH stack is 11.5 m longer in length than what was originally planned. Resulted in only 2 cm clearance from top BOP to moonpool roof.

What Was Planned

The space outs for WH, BOP, Riser, Diverter/Overshot to be as per planned Wellhead Stack up drawing from Well Partner.

What Was Learned

Ensure space out correctly in planning stage when its so crucial to operation.