No origin

Well

Tomcat
6501/10-1

Date created

2025/02/14
295 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
No classification

Deepsea Yantai


What happened in Surface section:
Tight spots which required up to 25 MT overpull to pull above.

What Was Planned

POOH with 26″ BHA

What Was Learned

DOP only planned for 15 MT overpull before taking remedial action. Generally, need more margin of overpull to work with in such a big diameter hole.

What Actions Are Required

For future reference plan with at least 20 – 25 MT overpull before taking remedial action.