What happened in Surface section:
Deep seat bucket takes a lot of rig time to install on drillfloor.

What Was Planned

Deep Seat Bucket for WH RT

What Was Learned

Possible to have it delivered from DQ with it installed? Reduces cargo handling, handling of tool offshore, reduces time and risk.
Alternatively install it on deck.

What Actions Are Required

DQ to deliver pre installed deep seat bucket for WH RT