By: Drilling Engineer

Report No.

5172

Discipline/Origin

No origin

Well

Carmen
35/10-10S

Date created

2023/05/07
944 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Equipment
Negative

Deepsea Yantai


What happened in Reservoir section:
Sent out a side door overshot from Archer last minute, but they did not have the grapples compatible with the cable head on all the tool strings.

What Was Planned

A side door overshot was not planned out for wireline operation.

What Was Learned

Should plan to send this out. Its good practice to have it onboard in case we get stuck with the wireline string and the automatics release on the surface does not work.

What Actions Are Required

Should plan to send this out. Its good practice to have it onboard in case we get stuck with the wireline string and the automatics release on the surface does not work.