WE Report

Lessons Learned

Lesson Learned





By: Lars Solvang

Report No.

2189

Discipline/Origin

Subsea
Own Experience

Well

Oselvar
A-1 H, A-2 H, A-3 HT2

Date created

2021/10/01
1528 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Equipment
Negative

Borgland Dolphin


What happened in P&A:
Two lubricator valves installed in the landing string.

What Was Planned

It was planned to have only one lubricator valve in the landing string

What Was Learned

It will not be possible to run in with wireline to set plugs and cut tubing with only one lubricator valves

What Actions Are Required

Plan for two lubricator valves from the start.