Lesson Learned



INTERNAL



No user selected

Report No.

393

Discipline/Origin

Drilling
No origin

Well

Shrek
6507/5-9 S, 6507/5-9 A

Date created

2020/03/13
2094 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Planning
Negative

Deepsea Nordkapp


Section N/A. What happened:
WE not aligned internally in weekly project meetings with client.

What Was Planned

Weekly meeting with PGNiG only, no internal project meeting.

What Was Learned

Leaving a suboptimal impression by the client.

What Actions Are Required

Establish weekly internal project meeting to ensure that all WE personnel are on the same page before having weekly meeting with client