WE Report

Lessons Learned

Lesson Learned





By: Sander Schaathun

Report No.

5112

Discipline/Origin

Drilling
No origin

Well

Eirik (OMV)No well selected

Date created

2023/03/29
984 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
N/A

Deepsea Yantai


What happened in Reservoir section:
Did not provide desired slug effect.

What Was Planned

Slug pumping
Pumping slug as recommended by HPHT manual (3 m3 and 0.35 sg).

What Was Learned

Consider re-phrasing the manual.

What Actions Are Required

Consider to adjust HPHT manual on next HPHT well.

What Was Done

Two slugs with in total 5 m3 had to be pumped.

Additional Documentation


LL-from-Eirik-OMV.pdf