Lesson Learned





By: Drilling Engineer

Report No.

8266

Discipline/Origin

Drilling
No origin

Well

Tomcat
6501/10-1

Date created

2025/02/14
296 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Equipment
No classification

Deepsea Yantai


What happened in Surface section:
Had to run SMO on pipe due to too much heave.

What Was Planned

Run SMO

What Was Learned

Consider not planning SMO running as SIMOPS/background operation if we are drilling in wintertime. Then we most likely will struggle to lift it down on a winch without compensator. ROV recommended 1m significant or less if winch shall be used.

What Actions Are Required

Take it into consideration next time planning a well / or time prediction.