Lessons Learned865


Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

Faroe
175 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 S
Brasse Appraisal
P&A 28/09/2017 8 hrs were used cutting the extension joints. During the cutting a high stick-slip was observed by . . .


PDF


Edit


DNO
1235 – DNO

Borgland Dolphin Other
PSA Findings
Other A-1 H, A-2 H, A-3 HT2
Oselvar
P&A 08/06/2017

Karina Helle / Morten Laget


PDF


Edit


DNO
1232 – DNO

Borgland Dolphin HSEQ
PSA Findings
Other A-1 H, A-2 H, A-3 HT2
Oselvar
P&A 11/11/2016

Karina Helle / Morten Laget