Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

PGNiG
348 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Surface section 22/10/2019 XBAT was run on 17 1/2″ BHA regardless.


PDF


Edit


PGNiG
358 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Production section 22/10/2019
Backup 12 ¼” BHA tools not testing correctly (XBAT, PWD and HCIM)
Shipped out new backup XBAT and . . .


PDF


Edit


PGNiG
362 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019
Drilled to core point and POOH. Experienced tool problems on ADR and XBAT (Sonic). HAL onshore was . . .


PDF


Edit


PGNiG
363 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019 Time consuming to test HAL MWD tools onboard.


PDF


Edit


PGNiG
364 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019 Time consuming to handle and M/U BHA.


PDF


Edit


PGNiG
365 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019 Racked core barrels, saving rig time.


PDF


Edit