WE Report

Lessons Learned

Lessons Learned865


Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

Faroe
291 – Faroe

Transocean Arctic Drilling Operational 31/7-3 A
Brasse
Reservoir section 03/10/2019 It took 5 hours to drill the wiper plugs in the Weatherford liner. This is twice as long as normal. . . .


PDF


Edit


Faroe
292 – Faroe

Transocean Arctic Drilling Operational 31/7-3 A
Brasse
Reservoir section 03/10/2019 Stuck with wireline toolstring 1A ZAIT-PEX-PPC-MSIP-PPC-NGI-XPT at 2831 m, bottom of toolstring and . . .


PDF


Edit


Faroe
293 – Faroe

Transocean Arctic Drilling Operational 31/7-3 A
Brasse
Reservoir section 03/10/2019 Performed cut and thread operation to free stuck wireline cable and fish wireline toolstring 1A. . . .


PDF


Edit


Faroe
294 – Faroe

Transocean Arctic Drilling Operational 31/7-3 A
Brasse
Reservoir section 03/10/2019 After engaging fish in overshot an electrical release of cable head (ECRD) was planned. Due to . . .


PDF


Edit


Faroe
295 – Faroe

Transocean Arctic Drilling Operational 31/7-3 A
Brasse
Reservoir section 03/10/2019 Unable to release cable head after engaging fish -> reverse cut and thread operation next. . . .


PDF


Edit


Faroe
287 – Faroe

Transocean Arctic Drilling Operational 31/7-3 S
Brasse
Top hole 02/10/2019 Had to lay out one joint of fibreglass innerstring due to not able to M/U connection. No visible . . .


PDF


Edit


Faroe
288 – Faroe

Transocean Arctic Drilling Operational 31/7-3 S
Brasse
Top hole 02/10/2019 Had relatively short rig move where operations ended with OBM and next well started with WBM. . . .


PDF


Edit


Faroe
289 – Faroe

Transocean Arctic Drilling Operational 31/7-3 S
Brasse
Top hole 02/10/2019 Seabed visibility poor and current high when cementing 30″ conductor. Inclination on bullseyes . . .


PDF


Edit


Faroe
290 – Faroe

Transocean Arctic Drilling Operational 31/7-3 S
Brasse
Intermediate section 02/10/2019 Pumped 3 x 20 m3 pills at section TD vs 2 x 20 m3 pills programmed. Not sure if made a difference, . . .


PDF


Edit


Faroe
279 – Faroe

Transocean Arctic Drilling Operational 30/6-30
Rungne
P&A 01/10/2019 Had to remove top stabbing guide on IRN to be able to M/U MPT (45 cm handling pup below). Reason for . . .


PDF


Edit


Faroe
281 – Faroe

Transocean Arctic Drilling Operational 30/6-30
Rungne
P&A 01/10/2019 Bent two singles 5 1/2″ HWDP while tagging top of surfacec cement plug after pulling BOP.


PDF


Edit


Faroe
282 – Faroe

Transocean Arctic Drilling Operational 30/6-30
Rungne
P&A 01/10/2019 Thread on tension mandrel was damaged in town (used for connecting Weatherford MOST tool to rotary . . .


PDF


Edit


Faroe
284 – Faroe

Transocean Arctic Drilling Operational 30/6-30
Rungne
P&A 01/10/2019 The 18 3/4″ HP housing lock ring released after cutting the 20″ casing with 20 mt overpull. . . .


PDF


Edit


Faroe
273 – Faroe

Transocean Arctic Drilling Operational 30/6-30
Rungne
Intermediate section 30/09/2019 The 5 1/2″ DP handling pup made up to the 9 5/8″ casing hanger running tool was too short. The . . .


PDF


Edit


Faroe
274 – Faroe

Transocean Arctic Drilling Operational 30/6-30
Rungne
Intermediate section 30/09/2019 Tagged fill 30 m above casing hanger landing depth/ casing shoe 36 m off bottom. Washed heavy casing . . .


PDF


Edit


Faroe
275 – Faroe

Transocean Arctic Drilling Operational 30/6-30
Rungne
Intermediate section 30/09/2019 Unable to set 9 5/8″ seal assembly. Observed initial pressure increase but unable to pass 100-120 . . .


PDF


Edit


Faroe
276 – Faroe

Transocean Arctic Drilling Operational 30/6-30
Rungne
Intermediate section 30/09/2019 The overpull margin was down to only 26 mt at the end, while running the heavy and long 9 5/8″ . . .


PDF


Edit


Faroe
277 – Faroe

Transocean Arctic Drilling Operational 30/6-30
Rungne
Reservoir section 01/01/2019 Made first connection on core BHA #3. This 64 m core BHA would require 2 connections on bottom. . . .


PDF


Edit


Faroe
278 – Faroe

Transocean Arctic Drilling Operational 30/6-30
Rungne
Reservoir section 01/01/2019 During POOH with coring assembly #3, took 70 mt overpull at 3250 m. After pulling further 9 m, got a . . .


PDF


Edit


Faroe
158 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 S
Brasse Appraisal
Top hole 28/09/2017 Problems to close the 30″ side door elevator due to shackles. Removed shackles and connected the 500 . . .


PDF


Edit