Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

PGNiG
4923 – PGNiG

Deepsea Yantai Logistics
Own Experience
Planning 6608/1-1 S
Copernicus
Other 03/10/2022 With this focus the mobilization plan became a live document and with a weekly focus, ensuring all . . .

Johan Kjos-Hanssen / Morten Laget



PDF


Edit


PGNiG
4921 – PGNiG

Deepsea Yantai Logistics
Own Experience
Operational 6608/1-1 S
Copernicus
Other 20/09/2022 Due to late busy vessel schedule of PSV and MI Swaco vessel MS Norbar, mud for 8-1/2″ Section was . . .

Johan Kjos-Hanssen / Morten Laget



PDF


Edit


PGNiG
4902 – PGNiG

Deepsea Yantai Logistics Operational 6608/1-1 S
Copernicus
Top hole 15/09/2022 It was sent out personell who had not been on the rig before and was not experienced with the . . .

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4846 – PGNiG

Deepsea Yantai Logistics Operational 6608/1-1 S
Copernicus
Reservoir section 12/09/2022 The BU GVR MWD tool for 8 1/2″ section not at site when drilling the section. The near bit . . .

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4922 – PGNiG

Deepsea Yantai Logistics
Own Experience
Operational 6608/1-1 S N/A 12/09/2022 Captain of the vessel suggested to use the Brine tank for the Premix as Premix does not contain . . .

Johan Kjos-Hanssen / Morten Laget



PDF


Edit


PGNiG
4840 – PGNiG

Deepsea Yantai Logistics
Own Experience
Operational 6608/1-1 S
Copernicus
Top hole 04/09/2022 With good planning and cooperation, everything shipped to SSJ prior to operation start in due time. . . .

Johan Kjos-Hanssen / Morten Laget



PDF


Edit