Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

DNO
1374 – DNO

Borgland Dolphin Drilling
Own Experience
INTERNAL
Planning A-1 H, A-2 H, A-3 HT2
Oselvar
Other 19/03/2021
Extremely time-consuming compared to what we get in return. Render design (or just Pia . . .

Steinar Aarnes / Morten Laget


PDF


Edit


DNO
1345 – DNO

Borgland Dolphin HSEQ
PSA Q&A
Planning A-1 H, A-2 H, A-3 HT2
Oselvar
N/A 11/02/2021

Vernetjenesten i Dolphin Drilling har en kommentar i deres uttalelse til samtykket. Vi ber om . . .

Karina Helle / Morten Laget


PDF


Edit


DNO
1346 – DNO

Borgland Dolphin Subsurface
PSA Q&A
Planning A-1 H, A-2 H, A-3 HT2
Oselvar
Reservoir section 11/02/2021

Det vil bli tatt prøver av gassbobler i forbindelse med marine operasjoner i forkant av oppstart . . .

Karina Helle / Morten Laget


PDF


Edit


DNO
1347 – DNO

Borgland Dolphin Marine
PSA Q&A
Planning A-1 H, A-2 H, A-3 HT2
Oselvar
N/A 11/02/2021

På vårt spørsmål om andre radarantenner vil bidra i overvåkningen med Smartblue utover . . .

Karina Helle / Morten Laget


PDF


Edit


DNO
1348 – DNO

Borgland Dolphin Marine
PSA Q&A
Planning A-1 H, A-2 H, A-3 HT2
Oselvar
Reservoir section 11/02/2021

Det er for øvrig ikke arkivert noe utdypende informasjon om Smartblue systemet hos oss, etter . . .

Karina Helle / Morten Laget


PDF


Edit


DNO
1177 – DNO

Borgland Dolphin HSEQ Planning A-1 H, A-2 H, A-3 HT2
Oselvar
N/A 10/02/2021 Reactivation and emergency preparedness has been challenging

Karina Helle / Morten Laget



PDF


Edit


DNO
1085 – DNO

Borgland Dolphin C&P Planning 2/5-15
Gomez
Other 08/02/2021 Slow progress, time-consuming with changes in template/process, and receiving PO’s late. Update of . . .

Morten Laget


PDF


Edit


DNO
986 – DNO

Borgland Dolphin Other Planning A-1 H, A-2 H, A-3 HT2
Oselvar
N/A 05/11/2020 Went through the detailed operational steps early in the planning phase (DG2) with relevant . . .

Øystein Prytz


PDF


Edit


DNO
972 – DNO

No Rig Drilling
INTERNAL
Planning No well
Gomez
N/A 17/10/2020 No kickoff or handover to the Well Management team.

Morten Laget


PDF


Edit


DNO
296 – DNO

Island Innovator Drilling Planning 6507/7-16 S
Canela
N/A 07/01/2019 Did not include the sidetracks.


PDF


Edit


DNO
299 – DNO

Island Innovator Drilling Operational 6507/7-16 S
Canela
N/A 07/01/2019 Did not have updated presentation for the meetings, after scope change of well.


PDF


Edit


DNO
303 – DNO

Island Innovator Drilling Planning 6507/7-16 S
Canela
N/A 07/01/2019 Geological target boxes developed late in planning phase. This resulted in less time for evaluating . . .


PDF


Edit