WE Report

Lessons Learned

Lessons Learned865


Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

DNO
6767 – DNO

Nobel Invincible Logistics Planning 2/6-7 S
Falstaff
Top hole 23/09/2024 Excellent planning. Safely executed. Experienced and knowledgeable Expro crews who cooperated good . . .

Lene Lomeland


PDF


Edit


DNO
2196 – DNO

Borgland Dolphin Logistics 2/5-15
Gomez
04/10/2021 Backloaded with lack of information. Sent to wrong vendor/handled wrong. The casing was mistakenly . . .

Martin Vikse / Morten Laget


PDF


Edit


DNO
2305 – DNO

Borgland Dolphin Logistics
Own Experience
Operational 2/5-15
Gomez
P&A 15/09/2021 Missing Protectors for 13-3/8″ Casing

Johan Kjos-Hanssen / Morten Laget



PDF


Edit


DNO
2094 – DNO

Borgland Dolphin Logistics
Own Experience
Operational 2/5-15
Gomez
Reservoir section 23/08/2021 Prior to mobilization of 8-1/2″ BHA, Coring and Wireline tools we held a aligmnement meeting to . . .

Johan Kjos-Hanssen


PDF


Edit


DNO
2117 – DNO

Borgland Dolphin Logistics
Own Experience
Operational A-1 H, A-2 H, A-3 HT2
Oselvar
Other 13/07/2021 Did not not get enough plates from rig and.

Johan Kjos-Hanssen / Stig Seland



PDF


Edit


DNO
1916 – DNO

Borgland Dolphin Logistics
Own Experience
Operational A-1 H, A-2 H, A-3 HT2
Oselvar
P&A 23/06/2021 Cleaning of pulled XMT onshore at base. Major onshore handling operations.

Johan Kjos-Hanssen / Stig Seland



PDF


Edit


DNO
1532 – DNO

Borgland Dolphin Logistics
Own Experience
Operational A-1 H, A-2 H, A-3 HT2
Oselvar
Other 26/05/2021 Delay on helicpoter with 3,5 hours. People hungry at the heliport and miss out the Lunch onboard the . . .

Johan Kjos-Hanssen / Stig Seland



PDF


Edit


DNO
1531 – DNO

Borgland Dolphin Logistics
Own Experience
Planning A-1 H, A-2 H, A-3 HT2
Oselvar
N/A 21/05/2021 Max PAX during operations landed on 16 PAX in even good flying conditions and personnel was bumped . . .

Johan Kjos-Hanssen / Stig Seland



PDF


Edit


DNO
1394 – DNO

Borgland Dolphin Logistics
Own Experience
INTERNAL
Operational A-3 HT2
Oselvar
Subsea work 03/04/2021 The POB got maxed out and there were no Covid-19 emergency cabins available at the time. Also, a . . .

Drilling Engineer / Stig Seland



PDF


Edit


DNO
1386 – DNO

Borgland Dolphin Logistics
Own Experience
Operational A-1 H, A-2 H, A-3 HT2
Oselvar
Subsea 29/03/2021
During operations things got delayed and went missing in the transport route (Aker fuses for . . .

Drilling Engineer / Stig Seland



PDF


Edit


DNO
1062 – DNO

Island Innovator Logistics Operational 6507/7-16 S
Canela
05/02/2021 Several days with HK delay because of seastate 6 resitrictions and HTI warning. Afternoon Flight . . .

Johan Kjos-Hanssen



PDF


Edit


DNO
1163 – DNO

Borgland Dolphin Logistics
Experience Transfer Meeting
Operational A-1 H, A-2 H, A-3 HT2
Oselvar
N/A 08/09/2020
Experience transfer meeting, Schooner & Ketch: Efficient mibilisation and backload
Minimal best . . .

Karina Helle / Morten Laget



PDF


Edit


DNO
1064 – DNO

Island Innovator Logistics Operational 6507/7-16 S
Canela
Top hole 04/12/2019 Pilot hole challenges required alot of extra Barite, more than what was planned to have onboard the . . .

Johan Kjos-Hanssen


PDF


Edit


New Lesson Learned