Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

PGNiG
346 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Surface section 22/10/2019 IKM MRR: missing hoses between LARS and 90 degrees flowbend topside. Backloaded by Mi Swaco.


PDF


Edit


PGNiG
347 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Surface section 22/10/2019 Exhaust from IKM generator causing fumes and issues being in cement office


PDF


Edit


PGNiG
349 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Surface section 22/10/2019 Elevator bushing for 13 3/8″ casing was missing on rig (backup to CRTi tool). This message was . . .


PDF


Edit


PGNiG
350 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Surface section 22/10/2019
Unable to make up Dril-Quip 13 3/8” no cross coupling (VAM 21) to WH assembly (VAM 21).
Had to . . .


PDF


Edit


PGNiG
351 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Surface section 22/10/2019
Silo #4 achieved desired pump rate (800 lpm) by opening the valves 7 %.
Silo #2 achieved same only . . .


PDF


Edit


PGNiG
359 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Production section 22/10/2019 Insite (Halliburton) could not handle NOV data, resulting in an overload and some NPT.


PDF


Edit


PGNiG
382 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Production section 22/10/2019 12-/4” drilling – parameters went well.


PDF


Edit