Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

PGNiG
406 – PGNiG

Deepsea Nordkapp Drilling
INTERNAL
Planning 6507/5-9 S, 6507/5-9 A
Shrek
N/A 13/03/2020 Vallourec – RfQ vs. Actual cost not comparable due to long lead time and spud date changes. Express . . .


PDF


Edit


PGNiG
407 – PGNiG

Deepsea Nordkapp Drilling
INTERNAL
Planning 6507/5-9 S, 6507/5-9 A
Shrek
N/A 13/03/2020 Dril-Quip – new cost items appear on invoices, not covered in contract. 


PDF


Edit


PGNiG
408 – PGNiG

Deepsea Nordkapp Drilling
INTERNAL
Planning 6507/5-9 S, 6507/5-9 A
Shrek
N/A 13/03/2020 QC time limit between receiving final cost estimates from vendors and submitting final AFE


PDF


Edit


PGNiG
409 – PGNiG

Deepsea Nordkapp Drilling
INTERNAL
Planning 6507/5-9 S, 6507/5-9 A
Shrek
N/A 13/03/2020 Cost Tracking post-op


PDF


Edit


PGNiG
410 – PGNiG

Deepsea Nordkapp Drilling
INTERNAL
Planning 6507/5-9 S, 6507/5-9 A
Shrek
N/A 13/03/2020 Meetings with essential suppliers (KO, EoW etc.) – secure that all departments gets the needed . . .


PDF


Edit


PGNiG
336 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Rig move 21/10/2019 Due to AHV cost we moored prior to spudding due to vessels been on contract due to market situation


PDF


Edit


PGNiG
269 – PGNiG

Deepsea Nordkapp Drilling Planning 6507/5-9 S
Shrek
N/A 02/09/2019
The project was quite unorganized with a lot of revisions and outdated info provided to the . . .


PDF


Edit


PGNiG
332 – PGNiG

Deepsea Nordkapp Drilling Planning 6507/5-9 S, 6507/5-9 A
Shrek
Planning 29/07/2019 In order to ensure compliance with NORSOK, a verification of the conductor analysis was done by DNV . . .


PDF


Edit


PGNiG
266 – PGNiG

Deepsea Nordkapp Drilling Planning 6507/5-9 S
Shrek
N/A 25/06/2019 The team decided to use a Excel based well delivery plan.


PDF


Edit


PGNiG
267 – PGNiG

Deepsea Nordkapp Drilling Planning 6507/5-9 S
Shrek
N/A 25/06/2019 It was decided to involve a operational planner from Odfjell in the Shrek project to help out with . . .


PDF


Edit


PGNiG
330 – PGNiG

Deepsea Nordkapp Drilling Planning 6507/5-9 S, 6507/5-9 A
Shrek
Planning 25/06/2019 The team decided to use a Excel based well delivery plan.


PDF


Edit


PGNiG
331 – PGNiG

Deepsea Nordkapp Drilling Planning 6507/5-9 S, 6507/5-9 A
Shrek
Planning 25/06/2019 It was decided to involve a operational planner from Odfjell in the Shrek project to help out with . . .


PDF


Edit