Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

PGNiG
6747 – PGNiG

Deepsea Yantai Marine
Own Experience
Operational 6501/10-1
Tomcat
Pre-Lay 15/09/2024
We started on anchor 4. This anchor was together with anchor 5 and 6 supposed to be installed to . . .

Stian Engvik / Stig Seland


PDF


Edit


PGNiG
6223 – PGNiG

Deepsea Yantai HSEQ
Own Experience
Planning 6501/10-1
Tomcat
Other 08/05/2024
An evaluation of some changes was not documented.
A MOC process should cover any RELEVANT changes . . .

Åse Kristin Pettersen / Stig Seland


PDF


Edit


PGNiG
6874 – PGNiG

No Rig Other
Own Experience
Planning 6501/10-1
Tomcat
N/A 06/11/2023 It is strong currents at the location, and it was very hard to keep the ROV stable when surveying . . .

Anniken Meisler / Anniken Meisler



PDF


Edit


PGNiG
5838 – PGNiG

Deepsea Yantai External Environment Planning 6501/10-1
Tomcat
Environmental Seabed inspection 19/06/2023 During preparation of SoW, Marine department needed input from Engineering Company (InterMoor) to . . .

Stian Engvik / Morten Laget



PDF


Edit


PGNiG
5834 – PGNiG

Deepsea Yantai Drilling
Own Experience
Planning 6305/10-1
Tomcat
N/A 15/06/2023
BO&K Analysis performed in Aug 2022, with a sensitivity on revised reservoir data.

The . . .

Richard Mollison / Morten Laget



PDF


Edit


PGNiG
4946 – PGNiG

Deepsea Yantai Drilling
Experience Transfer Meeting
Operational 6608/1-1 S
Copernicus
Production section 03/11/2022
The gas readings for the 12 ¼” was done very well, and the correlation was quite good between the . . .

Richard Mollison



PDF


Edit


PGNiG
4914 – PGNiG

Deepsea Yantai HSEQ
Own Experience
INTERNAL
End of Well 6608/1-1 S
Copernicus
Other 26/09/2022 We didn’t ask of information from the DSV during the operation

Åse Kristin Pettersen / Morten Laget


PDF


Edit


PGNiG
4912 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
Production section 20/09/2022 Time was spend circulating hole clean and even MW in/out.

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4907 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
17/09/2022 During bulking the boat was alongside and was covered in dust

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4905 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
P&A 16/09/2022 To balanced the cement plug by pumping more spacer behind the cement plug.

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4902 – PGNiG

Deepsea Yantai Logistics Operational 6608/1-1 S
Copernicus
Top hole 15/09/2022 It was sent out personell who had not been on the rig before and was not experienced with the . . .

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4903 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
Top hole 15/09/2022 Enhanced and ROV had to be on same channel as drillfloor when doing offline activity due to repeater . . .

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4904 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
Surface section 15/09/2022 The cement swivel was delivered with the wrong threads. Delivered with NC50, should been XT57.

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4950 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
Surface section 15/09/2022 The box end of the 13 3/8″ no cross coupling is too long to allow the use of the casing running tool . . .

Richard Mollison


PDF


Edit


PGNiG
4901 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
P&A 14/09/2022 The heating cabinet in the logging unit does not work as required, not able to change the . . .

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4846 – PGNiG

Deepsea Yantai Logistics Operational 6608/1-1 S
Copernicus
Reservoir section 12/09/2022 The BU GVR MWD tool for 8 1/2″ section not at site when drilling the section. The near bit . . .

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4845 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
Production section 11/09/2022 Ran casing hanger through rotary and installed master bushing. Difficult to install due to short . . .

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4834 – PGNiG

Deepsea Yantai Drilling
Own Experience
Planning 6608/1-1 S
Copernicus
Other 04/09/2022 When running of 20″ x 13 3/8″ casing was planned to be on Sunday 4/9/22 we tried to get surge . . .

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4835 – PGNiG

Deepsea Yantai Drilling
Own Experience
Operational 6608/1-1 S
Copernicus
Surface section 04/09/2022
When the rig reached a TD of 1100 m and no contingency 4-string design was needed anymore, the 20″ . . .

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4841 – PGNiG

Deepsea Yantai Drilling
Own Experience
Operational 6608/1-1 S Intermediate section 04/09/2022 Had to switch to a BX elevator

Drilling Engineer / Morten Laget


PDF


Edit