Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

PGNiG
403 – PGNiG

Deepsea Nordkapp Drilling
INTERNAL
Planning 6507/5-9 S, 6507/5-9 A
Shrek
N/A 13/03/2020 Invoice approver not familiar with RfQ for Drilling Services


PDF


Edit


PGNiG
404 – PGNiG

Deepsea Nordkapp Drilling
INTERNAL
Planning 6507/5-9 S, 6507/5-9 A
Shrek
N/A 13/03/2020 Pro-forma invoice check & approval process – supposed to use max. 5 working days, overrun for . . .


PDF


Edit


PGNiG
405 – PGNiG

Deepsea Nordkapp Drilling
INTERNAL
Planning 6507/5-9 S, 6507/5-9 A
Shrek
N/A 13/03/2020 Invoice approval PGNiG internal invoices (non-WE contracts), time consuming and extra work


PDF


Edit


PGNiG
406 – PGNiG

Deepsea Nordkapp Drilling
INTERNAL
Planning 6507/5-9 S, 6507/5-9 A
Shrek
N/A 13/03/2020 Vallourec – RfQ vs. Actual cost not comparable due to long lead time and spud date changes. Express . . .


PDF


Edit


PGNiG
407 – PGNiG

Deepsea Nordkapp Drilling
INTERNAL
Planning 6507/5-9 S, 6507/5-9 A
Shrek
N/A 13/03/2020 Dril-Quip – new cost items appear on invoices, not covered in contract. 


PDF


Edit


PGNiG
408 – PGNiG

Deepsea Nordkapp Drilling
INTERNAL
Planning 6507/5-9 S, 6507/5-9 A
Shrek
N/A 13/03/2020 QC time limit between receiving final cost estimates from vendors and submitting final AFE


PDF


Edit


PGNiG
409 – PGNiG

Deepsea Nordkapp Drilling
INTERNAL
Planning 6507/5-9 S, 6507/5-9 A
Shrek
N/A 13/03/2020 Cost Tracking post-op


PDF


Edit


PGNiG
410 – PGNiG

Deepsea Nordkapp Drilling
INTERNAL
Planning 6507/5-9 S, 6507/5-9 A
Shrek
N/A 13/03/2020 Meetings with essential suppliers (KO, EoW etc.) – secure that all departments gets the needed . . .


PDF


Edit


PGNiG
387 – PGNiG

Deepsea Nordkapp Rig Intake Operational 6507/5-9 S, 6507/5-9 A
Shrek
N/A 04/02/2020 Not able to get access to sublease contracts (NOV with wired pipe, Oceaneering cost)


PDF


Edit


PGNiG
388 – PGNiG

Deepsea Nordkapp Rig Intake Operational 6507/5-9 S, 6507/5-9 A
Shrek
N/A 04/02/2020 Contractor’s onshore organisation was very stretched in order to serve three customers (AkerBP, . . .


PDF


Edit


PGNiG
389 – PGNiG

Deepsea Nordkapp Rig Intake Operational 6507/5-9 S, 6507/5-9 A
Shrek
N/A 04/02/2020 Rig sublease


PDF


Edit


PGNiG
390 – PGNiG

Deepsea Nordkapp Rig Intake Operational 6507/5-9 S, 6507/5-9 A
Shrek
N/A 04/02/2020 PGNiG selected a PSV from AkerBP (Normand Skude) that was not performing very well. It turns out . . .


PDF


Edit


PGNiG
391 – PGNiG

Deepsea Nordkapp Rig Intake Operational 6507/5-9 S, 6507/5-9 A
Shrek
N/A 04/02/2020 Wellexpertise did not have staff onboard (ie. Drilling or logstics engneer or DSV’s). DEs not . . .


PDF


Edit


PGNiG
342 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Pilot hole section 22/10/2019 BHA modules coming out with various lifting subs.


PDF


Edit


PGNiG
343 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Surface section 22/10/2019 Unable to locate XO sub (DC58/TT550 NOV/Intelserv) offshore for 17 ½” BHA. New crossover had to be . . .


PDF


Edit


PGNiG
344 – PGNiG

Deepsea Nordkapp Drilling
INTERNAL
Operational 6507/5-9 S, 6507/5-9 A
Shrek
Surface section 22/10/2019 WDP did not enhance the Shrek drilling operations in any significant capacity


PDF


Edit


PGNiG
345 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Surface section 22/10/2019 IKM MRR 300 system (modified in lack of 500 system), failed to deliver adequate flow (3500lpm), . . .


PDF


Edit


PGNiG
346 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Surface section 22/10/2019 IKM MRR: missing hoses between LARS and 90 degrees flowbend topside. Backloaded by Mi Swaco.


PDF


Edit


PGNiG
347 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Surface section 22/10/2019 Exhaust from IKM generator causing fumes and issues being in cement office


PDF


Edit


PGNiG
348 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Surface section 22/10/2019 XBAT was run on 17 1/2″ BHA regardless.


PDF


Edit