Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

Wellesley
5130 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Surface section 10/04/2023

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5131 – Wellesley

No Rig Drilling Operational No well Surface section 10/04/2023 Difficulties passing 20″ CSG shoe through FMS. Engaged CRTi and pushed through.

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5132 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Surface section 10/04/2023 Lubricated OOH with 26″ BHA with 2000 lpm

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5133 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Surface section 10/04/2023 MWD/DD instructed drilling crew to break wrong connection when L/D 26″ BHA. As top part of assy was . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5134 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Surface section 10/04/2023 It was difficult to stab in the 20″ casing joints with 15 ft bails and rig movement

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5121 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Surface section 09/04/2023 Did not observe a shoulder making the casing up to 27 500 ft-lbs.

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5122 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Surface section 09/04/2023 The shoetrack was made up to 27,500 ft.lbs.

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5123 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Surface section 09/04/2023 The centralizers was placed close to the bottom of the casing joint and was difficult to handle on . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5113 – Wellesley

Deepsea Yantai Drilling Operational Eirik (OMV) Top hole 30/03/2023 Installation took about 0,5-0,75 hr rigtlme due to conductor movement and work above sea. . . .

Sander Schaathun / Morten Laget


PDF


Edit


Wellesley
5114 – Wellesley

Deepsea Yantai Drilling Operational Eirik (OMV) Intermediate section 30/03/2023 Experienced higher pore pressure earlier than expected. Had enough to weight up active from 1,44 to . . .

Sander Schaathun / Morten Laget


PDF


Edit


Wellesley
5115 – Wellesley

Deepsea Yantai Drilling Operational Eirik (OMV) Production section 30/03/2023 If we are leaning to one of the sides it is easy to hang up in something which can result in a . . .

Sander Schaathun / Morten Laget


PDF


Edit


Wellesley
5116 – Wellesley

Deepsea Yantai Drilling Operational Eirik (OMV) Reservoir section 30/03/2023
Change of slips due to damage of pump in sub connection.
Due to the low ROP the pump in sub side . . .

Sander Schaathun / Morten Laget


PDF


Edit


Wellesley
5112 – Wellesley

Deepsea Yantai Drilling Operational Eirik (OMV) Reservoir section 29/03/2023 Did not provide desired slug effect.

Sander Schaathun / Morten Laget


PDF


Edit


Wellesley
3373 – Wellesley

Borgland Dolphin Marine
Own Experience
Operational 36/1-4
Hemispheres
Rig move 18/02/2022 Uncontrolled runout of anchor and chain

Stian Engvik / Morten Laget



PDF


Edit


Wellesley
3246 – Wellesley

Borgland Dolphin Drilling
Own Experience
Operational 36/1-4
Hemispheres
P&A 29/01/2022
Cement plug was pumped without incident, POOH through cement was without incident. Circulated clean . . .

Drilling Supervisor / Morten Laget



PDF


Edit


Wellesley
3241 – Wellesley

Borgland Dolphin HSEQ
Own Experience
Operational 36/1-4
Hemispheres
N/A 28/01/2022 There was a dropped object (DO) incident onboard BGL, and DO is not included in the reporting & . . .

Anniken Meisler / Morten Laget


PDF


Edit


Wellesley
2413 – Wellesley

Borgland Dolphin Drilling
Own Experience
Operational 36/1-4
Hemispheres
Surface section 04/01/2022
Ahead of a connection at 1146m (105m below the 13 3/8″ shoe), a blockage occurred in the cuttings . . .

Drilling Supervisor / Morten Laget


PDF


Edit


Wellesley
2409 – Wellesley

Borgland Dolphin Drilling
Own Experience
Operational 36/1-4
Hemispheres
Top hole 01/01/2022 When making up 18 3/4″ WHH to No Cross joint it was very tight clearance for upper and lower jaws to . . .

Drilling Supervisor / Morten Laget


PDF


Edit


Wellesley
2401 – Wellesley

Borgland Dolphin Drilling
Own Experience
Operational 36/1-4
Hemispheres
Production section 30/12/2021 ALL mud skips was put on the same boat, effectively removing any hope for recieving backload on said . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
2347 – Wellesley

Borgland Dolphin Logistics
Own Experience
Operational 36/1-4
Hemispheres
Top hole 28/12/2021
Saga Fjordbase took the 75ft riser joint and backloaded in addition to the 30″ conductor joints. The . . .

Drilling Engineer / Morten Laget


PDF


Edit