Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

PGNiG
369 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019 Difficult to decide on placement of centralizers for racking since the casing joints vary in lengths . . .


PDF


Edit


PGNiG
370 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019 Reduced torque when drilling out shoetrack resulting in less efficiency.


PDF


Edit


PGNiG
371 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019 StormGeo faultly predicted the upcoming weather, resulting in new decisions being made based on . . .


PDF


Edit


PGNiG
372 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019 Problems with gas readings from gas trap with flow less than 2000 lpm. Gas trap installed in flow . . .


PDF


Edit


PGNiG
373 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019
Odfjell changing out parts of Management (TSL, DSL, OIM) to attend 3 day leadership seminar onshore. . . .


PDF


Edit


PGNiG
374 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019 Getting OBM sent out lith a low O/W ratio (70/30).


PDF


Edit


PGNiG
375 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019 Cores were retrieved successfully.


PDF


Edit


PGNiG
376 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019 Coal was discovered in reservoar, resulting in stuck core barrels on annulus.


PDF


Edit


PGNiG
377 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019 Waited for 30 minutes for annular relaxation after a P/T.


PDF


Edit


PGNiG
378 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Production section 22/10/2019 Issues recovering the OH 9-5/8” csg (in preparation for ST). Swabbing in annulus and back flow up . . .


PDF


Edit


PGNiG
379 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Production section 22/10/2019 Cut of 9-5/8” casing close to/above uncemented weak sand interval (w/ minor 5% gas). Resulted in . . .


PDF


Edit


PGNiG
380 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019 Circulating after releasing 9-5/8” hgr.


PDF


Edit


PGNiG
381 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019 Circulating beneath annular for potential gas (ie on pulling seal assy)


PDF


Edit


PGNiG
382 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Production section 22/10/2019 12-/4” drilling – parameters went well.


PDF


Edit


PGNiG
383 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Production section 22/10/2019 Had to stop operations to fix a leak in TDX s-pipe connection – 2x o-rings.


PDF


Edit


PGNiG
384 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Production section 22/10/2019 NOV software did not include the PGNiG well so PGNiG personnel unable to see it – only seen in . . .


PDF


Edit


PGNiG
385 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Production section 22/10/2019 Excellent mud performance throughout operations. Issues with O/W ratio due to topside issues.


PDF


Edit


PGNiG
386 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Production section 22/10/2019 Excellent cement performances throughout operations (except the first KOP due to losses, weak . . .


PDF


Edit


PGNiG
335 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Rig move 21/10/2019 The c-plate was onshore and put on spud boat just in time.


PDF


Edit


PGNiG
336 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Rig move 21/10/2019 Due to AHV cost we moored prior to spudding due to vessels been on contract due to market situation


PDF


Edit