Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

DNO
8328 – DNO

Deepsea Yantai Drilling Operational 35/10-13
Kjøttkake
Surface section 20/02/2025 Having KCL level at 200 kg/m3 was a success factor to drilling section.

Stein-Petter Slatlem


PDF


Edit


DNO
5919 – DNO

Deepsea Yantai Drilling Operational 25/7-11 S
Norma
N/A 10/09/2023 Done as per plan. For the coring operations a new LCM pill was mixed. The LCM from the 8 1/2″ . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5174 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Reservoir section 08/05/2023 Treated the mud for the second and subsequent runs circulating BU after cutting cores.

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5161 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Reservoir section 26/04/2023 Weighted up the mud by mixing in a heavier mud. The volume of heavier mud can partially compensate . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5159 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Production section 24/04/2023
Downtime due to reduced ROP after going to max ROP of 75 m/hr:
– Started with 30 m/hr
– Jumped up . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5160 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Production section 24/04/2023
Lube mud had 1.34 sg when taken up.
Needed to weight it down to ± 1.25 sg.
New lube mud for 12 . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5114 – Wellesley

Deepsea Yantai Drilling Operational Eirik (OMV) Intermediate section 30/03/2023 Experienced higher pore pressure earlier than expected. Had enough to weight up active from 1,44 to . . .

Sander Schaathun / Morten Laget


PDF


Edit


PGNiG
4834 – PGNiG

Deepsea Yantai Drilling
Own Experience
Planning 6608/1-1 S
Copernicus
Other 04/09/2022 When running of 20″ x 13 3/8″ casing was planned to be on Sunday 4/9/22 we tried to get surge . . .

Drilling Engineer / Morten Laget


PDF


Edit


INEOS
2273 – INEOS

Borgland Dolphin Logistics
Own Experience
Operational 6306/3-1 S
Fat Canyon
Production section 05/11/2021 During operation drilling did go slower than expected and way too often the boats has to go to the . . .

Drilling Engineer / Morten Laget


PDF


Edit


DNO
1930 – DNO

Borgland Dolphin Drilling
Own Experience
Operational A-1 H, A-2 H, A-3 HT2
Oselvar
P&A 29/06/2021 We had a lot of friction in a long and deviated well A3 with brine.

Drilling Supervisor / Stig Seland



PDF


Edit


Wellesley
259 – Wellesley

Transocean Arctic Drilling Operational 35/4-2
Songesand
Reservoir section 16/06/2020 The cold temperature in the riser and 300 m below seabed made the WBM more viscous than under normal . . .


PDF


Edit


PGNiG
368 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019 Drilled 8 1/2″ section with 1.30 sg MW. Based on LWD data from 12 ¼” the predicted PP in the 8 ½” . . .


PDF


Edit


PGNiG
374 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Reservoir section 22/10/2019 Getting OBM sent out lith a low O/W ratio (70/30).


PDF


Edit


PGNiG
385 – PGNiG

Deepsea Nordkapp Drilling Operational 6507/5-9 S, 6507/5-9 A
Shrek
Production section 22/10/2019 Excellent mud performance throughout operations. Issues with O/W ratio due to topside issues.


PDF


Edit


Wellesley
179 – Wellesley

Transocean Arctic Drilling Operational 35/12-7
Serin
Surface section 05/02/2019 The cuttings were encapsulated with mud, very little hydration, dry and crisp inside.


PDF


Edit


DNO
301 – DNO

Island Innovator Drilling Planning 6507/7-16 S
Canela
N/A 07/01/2019 DNO subsurface department wanted to use new OBM for drilling the sidetrack reservoir section.


PDF


Edit


DNO
312 – DNO

Island Innovator Drilling Planning 6507/7-16 S
Canela
Intermediate section 07/01/2019 The 17 1/2″ section was drilled, but it proved difficult to get hold of Glycol for the KCl mud.


PDF


Edit


DNO
314 – DNO

Island Innovator Drilling Operational 6507/7-16 S
Canela
Intermediate section 07/01/2019 KCl WBM was used for drilling the 17 1/2″ section to 1200 m. The hole was observed in good condition . . .


PDF


Edit


DNO
315 – DNO

Island Innovator Drilling Planning 6507/7-16 S
Canela
Intermediate section 07/01/2019 Had to increase MW from the planned 1.48 sg to 1.52 sg at TD due to cavings.


PDF


Edit


DNO
316 – DNO

Island Innovator Operational 6507/7-16 S
Canela
Production section 07/01/2019 Drilled section with planned mud and mud weight without problems with cavings. Cavaings identified . . .


PDF


Edit