Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

Wellesley
5185 – Wellesley

Deepsea Yantai Drilling
Own Experience
Operational 35/10-10S
Carmen
Reservoir section 18/05/2023 On second MDT got stuck with Saturn packer and had to release electrical cable head and fish . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5173 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Reservoir section 08/05/2023 Crew not participating in the pre-job meeting but involved in L/D core.

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5174 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Reservoir section 08/05/2023 Treated the mud for the second and subsequent runs circulating BU after cutting cores.

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5175 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Reservoir section 08/05/2023 Followed the HPHT manual for fingerprinting. Fingerprinter found some improvement point to the . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5176 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Reservoir section 08/05/2023 When coring 54 m cores, during connection the kick stand was removed a single joint was connected . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5162 – Wellesley

Deepsea Yantai Drilling Planning 35/10-10S
Carmen
Reservoir section 29/04/2023 Found some deviation in the DOP’s from the HPHT manual.

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5163 – Wellesley

Deepsea Yantai Drilling Planning 35/10-10S
Carmen
29/04/2023 There is to much information in the DOP’s. Easy to miss out on important steps because they are . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5161 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Reservoir section 26/04/2023 Weighted up the mud by mixing in a heavier mud. The volume of heavier mud can partially compensate . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5157 – Wellesley

Deepsea Yantai Drilling
Own Experience
Operational 35/10-10S
Carmen
Production section 24/04/2023 It was done before the cementer got the change to da a pre-job check / install bypass baffle etc.

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5158 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Reservoir section 24/04/2023
NPT: 7.75 hrs
Cost: 1 614 000 NOK

Cyber chair stopped functioning.
On Odfjell.

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5159 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Production section 24/04/2023
Downtime due to reduced ROP after going to max ROP of 75 m/hr:
– Started with 30 m/hr
– Jumped up . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5160 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Production section 24/04/2023
Lube mud had 1.34 sg when taken up.
Needed to weight it down to ± 1.25 sg.
New lube mud for 12 . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5143 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Surface section 16/04/2023
NPT: 1.25 hrs
Cost: 260 417 NOK
Downtime due to reaming and reduced ROP.
Drilled stand from . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5144 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Surface section 16/04/2023
NPT: 1.25 hrs
Cost: 260 417 NOK

Repaired hydraulic leak on PS-30 slips.

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5145 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Intermediate section 16/04/2023 FIT was a success. Shaved off 1.75 hrs compared to the test at 20″ shoe. 2.5 hrs vs 0.75 hrs. . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5142 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Surface section 14/04/2023
NPT: 0.75 hrs
Cost: 156 250 NOK
Downtime due to Work String/Jar/Stuck Equipment.
Freed stuck . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5138 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Surface section 13/04/2023
Total NPT: 11.25 hrs
Cost: 2 343 750 NOK

LARS lost communication with SubSea pump. Troubleshot . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5139 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Surface section 13/04/2023
NPT: 1.25 hrs
Cost: 260 417 NOK

Performed mechanical repair on make/break cylinder on casing . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5140 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Surface section 13/04/2023
NPT: 0.75 hrs
Cost: 156 250 NOK

Observed poor make-up of jt #204 into jt #111:
– No shoulder . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5141 – Wellesley

Deepsea Yantai Drilling
Own Experience
Operational 35/10-10S
Carmen
Intermediate section 13/04/2023 Not approved pressure test. Downtime to drilling contractor.

Drilling Engineer / Morten Laget



PDF


Edit