Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

Faroe
1112 – Faroe

Deepsea Bergen HSEQ
PSA Q&A
Planning 31/7-2, 31/7-3
Brasse Appraisal
N/A 09/02/2021

Hvor stor klaring har en fra dekket til bølgetoppen i hundreårsstorm?

Karina Helle / Morten Laget



PDF


Edit


Faroe
157 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 S
Brasse Appraisal
P&A 28/09/2017 Drilled 36″ hole with 36″ bit at 21 m/hr on bottom ROP without problems maintaining verticality.


PDF


Edit


Faroe
158 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 S
Brasse Appraisal
Top hole 28/09/2017 Problems to close the 30″ side door elevator due to shackles. Removed shackles and connected the 500 . . .


PDF


Edit


Faroe
159 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 S
Brasse Appraisal
Surface section 28/09/2017 Painted lengths on 13 3/8″ casing from town was actual lengths, not M/U lengths. This might cause . . .


PDF


Edit


Faroe
160 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 S
Brasse Appraisal
Surface section 28/09/2017 During M/U 18 3/4″ WHH, threads got cross threaded from side to side when moving the 18 3/4″ WHH. . . .


PDF


Edit


Faroe
161 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 S
Brasse Appraisal
Intermediate section 28/09/2017 Remote on Cement head did not work. Had to operate manually by man in riding belt. The tool worked . . .


PDF


Edit


Faroe
162 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 S
Brasse Appraisal
Reservoir section 28/09/2017
WL logs showed that the core point was in the Hardråde fm in the Shetland Gp and not in the Draupne . . .


PDF


Edit


Faroe
163 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 S
Brasse Appraisal
Reservoir section 28/09/2017 Stick clay was observed in the lower Fensfjord fm. Up to 22mt overpull was observed POOH, and a . . .


PDF


Edit


Faroe
164 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 S
Brasse Appraisal
Reservoir section 28/09/2017 Core jammed off after cutting 57m, not long after making a connection. Coring was started in the . . .


PDF


Edit


Faroe
165 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 S
Brasse Appraisal
Reservoir section 28/09/2017 Logged liner cement with USIT/CBL. Initial evaluation results offshore showed bad/no cement present. . . .


PDF


Edit


Faroe
166 – Faroe

Deepsea Bergen Well test Operational 31/7-2 S
Brasse Appraisal
N/A 28/09/2017 Running cable through cut out in master bushing


PDF


Edit


Faroe
167 – Faroe

Deepsea Bergen Well test Operational 31/7-2 S
Brasse Appraisal
N/A 28/09/2017 N/A


PDF


Edit


Faroe
168 – Faroe

Deepsea Bergen Well test Operational 31/7-2 S
Brasse Appraisal
N/A 28/09/2017 Changing out subsea test tree, from 10 to 15 k


PDF


Edit


Faroe
169 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 S
Brasse Appraisal
P&A 28/09/2017 In DOP for pulling 9 5/8″ seal assembly, it was planned “Pick up with 3 ton overpull to check MPT . . .


PDF


Edit


Faroe
170 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 A
Brasse Appraisal
Intermediate section 28/09/2017 During displacement from WBM to OBM (while drilling out cement), attempted to u-tube kill and choke . . .


PDF


Edit


Faroe
171 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 A
Brasse Appraisal
Intermediate section 28/09/2017 Skips were not practical and required a lot of manual handling to operate. The lids are heavy and . . .


PDF


Edit


Faroe
172 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 A
Brasse Appraisal
Intermediate section 28/09/2017
After making up the 9 5/8″ liner hanger circulation was attempted established with 2000 lpm. Losses . . .


PDF


Edit


Faroe
174 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 A
Brasse Appraisal
Reservoir section 28/09/2017 When logging the 9 5/8” casing cement it was discovered during a repeat pass that the cement logs . . .


PDF


Edit


Faroe
175 – Faroe

Deepsea Bergen Drilling Operational 31/7-2 S
Brasse Appraisal
P&A 28/09/2017 8 hrs were used cutting the extension joints. During the cutting a high stick-slip was observed by . . .


PDF


Edit


Faroe
1151 – Faroe

Deepsea Bergen HSEQ
PSA Q&A
Planning 31/7-2
Brasse Appraisal
N/A 16/04/2017

Hvem representerer henholdsvis arbeidsgiver og arbeidstaker for 3. part selskap i det felles . . .

Karina Helle / Morten Laget


PDF


Edit