Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

Wellesley
5123 – Wellesley

Deepsea Yantai Drilling Operational 35/10-10S
Carmen
Surface section 09/04/2023 The centralizers was placed close to the bottom of the casing joint and was difficult to handle on . . .

Drilling Engineer / Morten Laget


PDF


Edit


Wellesley
5113 – Wellesley

Deepsea Yantai Drilling Operational Eirik (OMV) Top hole 30/03/2023 Installation took about 0,5-0,75 hr rigtlme due to conductor movement and work above sea. . . .

Sander Schaathun / Morten Laget


PDF


Edit


Wellesley
5114 – Wellesley

Deepsea Yantai Drilling Operational Eirik (OMV) Intermediate section 30/03/2023 Experienced higher pore pressure earlier than expected. Had enough to weight up active from 1,44 to . . .

Sander Schaathun / Morten Laget


PDF


Edit


Wellesley
5115 – Wellesley

Deepsea Yantai Drilling Operational Eirik (OMV) Production section 30/03/2023 If we are leaning to one of the sides it is easy to hang up in something which can result in a . . .

Sander Schaathun / Morten Laget


PDF


Edit


Wellesley
5116 – Wellesley

Deepsea Yantai Drilling Operational Eirik (OMV) Reservoir section 30/03/2023
Change of slips due to damage of pump in sub connection.
Due to the low ROP the pump in sub side . . .

Sander Schaathun / Morten Laget


PDF


Edit


Wellesley
5112 – Wellesley

Deepsea Yantai Drilling Operational Eirik (OMV) Reservoir section 29/03/2023 Did not provide desired slug effect.

Sander Schaathun / Morten Laget


PDF


Edit


DNO
5097 – DNO

Deepsea Yantai Multi Discipline
Own Experience
INTERNAL
Planning 25/7-11 S Other 22/03/2023 Drilling Engineers have been using online software called The Engineering ToolBox. This software . . .

Stian Engvik / Morten Laget


PDF


Edit


PGNiG
4946 – PGNiG

Deepsea Yantai Drilling
Experience Transfer Meeting
Operational 6608/1-1 S
Copernicus
Production section 03/11/2022
The gas readings for the 12 ¼” was done very well, and the correlation was quite good between the . . .

Richard Mollison



PDF


Edit


PGNiG
4923 – PGNiG

Deepsea Yantai Logistics
Own Experience
Planning 6608/1-1 S
Copernicus
Other 03/10/2022 With this focus the mobilization plan became a live document and with a weekly focus, ensuring all . . .

Johan Kjos-Hanssen / Morten Laget



PDF


Edit


PGNiG
4948 – PGNiG

Deepsea Yantai External Environment
NEA Q&A
Planning 6608/1-1 S
Copernicus
Other 28/09/2022

Det kan forventes sporadisk fiskeriaktivitet med fartøy som fisker med konvensjonelt redskap etter . . .

Sanne Risbakk



PDF


Edit


PGNiG
4914 – PGNiG

Deepsea Yantai HSEQ
Own Experience
INTERNAL
End of Well 6608/1-1 S
Copernicus
Other 26/09/2022 We didn’t ask of information from the DSV during the operation

Åse Kristin Pettersen / Morten Laget


PDF


Edit


PGNiG
4951 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1
Copernicus
N/A 26/09/2022 The Electrician was called and he found a loose wire (norwegian: fase) inside one of the . . .

Steinar Aarnes



PDF


Edit


PGNiG
4913 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
P&A 23/09/2022 When pulling the conductor there was no cement stuck to it due to use of protane wrapping on the . . .

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4911 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
Surface section 20/09/2022
10-15 ton OP while pulling out of open hole.
Bit and stabs balled up / clay

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4912 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
Production section 20/09/2022 Time was spend circulating hole clean and even MW in/out.

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4921 – PGNiG

Deepsea Yantai Logistics
Own Experience
Operational 6608/1-1 S
Copernicus
Other 20/09/2022 Due to late busy vessel schedule of PSV and MI Swaco vessel MS Norbar, mud for 8-1/2″ Section was . . .

Johan Kjos-Hanssen / Morten Laget



PDF


Edit


PGNiG
4908 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
19/09/2022 Spent 3 hours to release RT after landed 18 3/4″ WH

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4909 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
Top hole 19/09/2022 The SMO level sensor did not function in auto operation. Was operated manually. Enhanced made a . . .

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4910 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
P&A 19/09/2022 After setting 8 1/2″ OH P&A Cement Plug the plan was to circulate clean at 100 m over TOC and . . .

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4907 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
17/09/2022 During bulking the boat was alongside and was covered in dust

Drilling Engineer / Morten Laget


PDF


Edit